|
HOW TO USE THIS BOOK
Paint
estimating is more of an art
than a science. There’s no
price that’s exactly right
for every job and for every
bidder. That’s because every
painting job is unique. No
single material cost, no
labor estimate, no pricing
system fits all types of
work. And just as every job
varies, so do painting
companies. No two painting
contractors have the same
productivity rates, the same
labor burden, the same
overhead expense and the
same profit requirements.
The
best paint estimates are
always custom-made for a
particular job. They’re
based on the contractor’s
actual productivity rate,
material cost, labor cost,
overhead percentage and
profit expectations. No
estimating book, no
computerized estimating
system, no estimating
service can possibly account
for all the variables that
make every job and every
painting company different.
Only a skilled estimator
using professional judgment
and a proven estimating
system can produce
consistently reliable
estimates on a wide variety
of painting jobs.
So,
Why Buy This Book?
That’s easy. This is the
most complete, authoritative
and reliable unit cost guide
ever made available to paint
estimators. No matter what
types of work you estimate,
no matter what your costs
are, this book will help
produce consistently
accurate painting cost
estimates in dollars and
cents. But it isn’t a
substitute for expertise.
It’s not a simple way to do
in minutes what an
experienced paint estimator
might not be able to do in
hours. Instead, this unit
cost guide will aid you in
developing a good estimate
of costs for any painting
operation on any project.
Think of this manual as one
good estimating tool. But
it’s not (or at least
shouldn’t be) the only
estimating tool you’ll use.
For
most jobs, I expect that the
figures you see here will
prove to be good estimates.
But anyone who understands
paint estimating will
understand why judgment is
needed when applying figures
from this manual — or any
other paint estimating
guide. It’s your
responsibility to decide
which conditions on the job
you’re bidding are like
conditions assumed in this
manual, and which conditions
are different. Where
conditions are different,
you’ll need good
professional judgment to
arrive at a realistic
estimated cost.
Inside
the back cover of this book
you’ll find an envelope with
a compact disk. The disk has
National Estimator, an
easy-to-use estimating
program with all the cost
estimates in this book.
Insert the CD in your
computer and wait a few
seconds. Installation should
begin automatically. (If
not, click Start, Settings,
Control Panel, double-click
Add/Remove programs and
Install.) Select ShowMe from
the installation menu and
Dan will show you how to use
National Estimator. When
ShowMe is complete, select
Install Program. When the
National Estimator program
has been installed, click
Help on the menu bar, click
Contents, click Print all
Topics, click File and click
Print Topic to print a
28-page instruction manual
for National Estimator.
Figure 1
The basis for painting
cost estimates in this
book.
|
|
Manhour
productivity |
Labor cost per
hour |
Labor burden
percent |
Labor burden
dollars |
Labor cost plus
burden |
Material price
discount |
Overhead percent |
Profit |
|
Slow (1P) |
Low |
$13.25 |
29.5% |
$3.98 |
$17.48 |
20% |
19.0% |
16% |
|
Medium (2P) |
Average |
19.50 |
35.4% |
6.90 |
26.40 |
30% |
25.0% |
12% |
|
Fast (3P) |
High |
25.50 |
40.8% |
10.40 |
35.90 |
40% |
31.0% |
7% |
|
Notes: These
rates are for
painters. Hourly
rates for
wallcovering are
different. See
page 29. Slow,
Medium and Fast
jobs are defined
on page 13.
Labor burden
percentages used
in this book are
summarized on
page 31.
National
Estimator uses
hourly rates in
the Labor cost
plus burden
column. National
Estimator shows
productivity
rates (Slow,
Medium and Fast)
and copies the
words Slow,
Medium or Fast
to your
estimate. It
also copies the
crew
productivity
code, either 1P
(Slow), 2P
(Medium), or 3P
(Fast) to your
estimating form.
National
Estimator allows
you to enter any
percentage you
select for
overhead and
profit. |
-
How to Use the Tables
The estimating tables in
this book show typical
costs and bid prices for
every painting operation
you’re likely to
encounter, whether paint
is applied by brush,
roller, mitt or spray.
Selecting the right cost
table and the correct
application method is
easy. Tables are divided
into four parts:
-
Part I: General
Painting Costs
-
Part II:
Preparation Costs
-
Part III:
Industrial,
Institutional and Heavy
Commercial Painting
Costs
-
Part IV:
Wallcovering Costs
Each
section is arranged
alphabetically by operation.
If you have trouble finding
the tables you need, use the
Table of Contents at the
front of the book or the
Index at the back of the
book.
Once
you’ve found the right table
and the appropriate
application method, you have
to select the correct
application rate. For each
of the application methods
(brush, roll, mitt or
spray), the tables show
three application rates:
“Slow,” “Medium,” or “Fast.”
That’s a very important
decision when using this
book, because each
application rate assumes
different manhour
productivity, material
coverage, material cost per
gallon, hourly labor cost,
labor burden, overhead and
profit. Your decision on the
application rate to use (or
which combination of rates
to use) has to be based on
your evaluation of the job,
your painters and your
company. That’s where good
common sense is needed.
Figure
1 shows crew codes, labor
costs, labor burdens,
material discounts, and
profit for each of the three
production rates for
painting.
The
“Slow” application rate in
Figure 1 assumes lower
productivity (less area
covered per manhour), a
lower labor cost (due to a
less skilled crew), a lower
labor burden (due to lower
fringe benefits), a lower
discount on materials
(because of low volume),
higher overhead (due to
lower volume) and a higher
profit margin (typical on
small repaint or custom
jobs). Figures in this
“Slow” application row will
apply where painters with
lower skill levels are
working on smaller or more
difficult repaint jobs.
Look
at the “Fast” row in Figure
1. These estimates will
apply where a skilled crew
(higher hourly rate and
larger fringe benefits) is
working under good
supervision and good
conditions (more area
covered per manhour) on
larger (volume discount on
materials) and more
competitive jobs (lower
profit margin). Figures in
the “Fast” application row
assume high productivity and
lower material coverage,
(unpainted surfaces absorb
more paint), like that of a
residential tract job.
Each
of the three application
rates is described more
completely later in this
section.
The
Easy Case: No Adjustments
Let’s suppose the “Slow”
application rate fits the
job you’re estimating almost
perfectly. Your crew’s
productivity is expected to
be low. The labor cost will
be $13.50 per hour. Labor
burden (fringes, taxes and
insurance) will be 29.5
percent. Discount on
materials will be 20
percent. Overhead will be 19
percent and profit will be
16 percent. Then your task
is easy. All of your costs
match the costs in the
“Slow” row. No modifications
are needed. The same is true
if your costs fit the
“Medium” or “Fast” rows.
But
that’s not always going to
happen. More often, the job,
your crew and your company
won’t fit exactly into any
of the three rows. What
then? More evaluation is
required. You’ll combine
costs from several
application rate rows to
reach an accurate bid price.
I call that customizing your
costs and it’s nearly always
required for an accurate
estimate.
Customizing Your Costs
Every company has a
different combination of
worker speed and experience,
taxes, benefits, spread
rates, equipment needs,
percentage for overhead, and
profit margin. These are the
cost variables in paint
estimating. This book is
designed so you can quickly
and easily adjust estimates
to reflect actual costs on
the job you’re estimating.
It’s important that you read
the rest of this section
before using the cost tables
in this book. That’s the
only way to get from this
manual all the accuracy and
flexibility that’s built
into it.
In the
remainder of this section
I’ll describe the
assumptions I’ve made and
the methods I used to
compile the cost tables in
this manual. Once you
understand them, you’ll be
able to combine and modify
costs in the estimating
tables so your bids fit the
job, your crew and your
company as closely as
possible.
When
you start using the cost
tables in this book, I
suggest you circle numbers
in the “Slow,” “Medium,” or
“Fast” application rate rows
that best fit your company
and your jobs. To improve
accuracy even more, write
your own figures in the
blank row below the “Fast”
row in each table, like I’ve
done in Figure 2.

A Practical Example
Figure 2 is part of an
estimating table taken from
Part I of this book, General
Painting Costs. I’m going to
use it to show how to
customize estimates to match
your actual costs. In Figure
2 I’ve circled some of the
costs I plan to use in a
sample estimate and
calculated others.
In
column 1, Labor SF per
manhour, I’ve circled
675 because I feel the
journeyman painter assigned
to this job can paint walls
at the “Fast” rate of 675
square feet per hour. That’s
the number I plan to use for
my estimate.
In
column 2, Material
coverage SF/gallon, I’ve
reviewed my past performance
and I expect coverage will
be about 275 square feet per
gallon of paint. So I’ve
circled that figure.
In
column 3, Material cost
per gallon, I’ve circled
21.90 for my cost per gallon
for flat water base latex
(including tax and an
allowance for consumable
supplies), based on a 30
percent discount from the
retail price.
So
far, so good. That completes
the first three columns,
what I call the pricing
variables. Now we can
begin on the unit cost
estimate, columns 4
through 9. Each of these
columns show a price per 100
square feet of wall.
We’ll
start with column 4, Labor
cost per 100 SF. Notice that
I’ve entered 3.11 for this
column. Here’s why. Look
back at Figure 1. Throughout
this book the painting labor
rate for “Fast” work is
assumed to be $25.75 per
hour. See page 29 for the
wallcovering application
rate. I can’t use the labor
cost per 100 SF for “Fast”
work because the journeymen
on my job earn $21.00 per
hour. That pay rate is
between the “Medium” and
“Fast” pay rates as shown in
Figure 1. To calculate the
labor cost per 100 SF,
divide $21.00 by 675 and
multiply by 100: 21/675 =
.0311 x 100 = 3.11.
In
column 5, Labor burden
100 SF, I’ve entered
.92. This figure is a result
of my labor cost at $3.11 x
29.5 percent, my labor
burden (taxes, insurance and
benefits) from the “Slow”
row of Figure 1. Even though
the labor rate is “Fast” and
the labor cost is between
“Fast” and “Medium,” for
this example labor burden
will be most like work done
at the “Slow” rate because
this company doesn’t offer
many benefits.
In
column 6, Material cost
per 100 SF, I’ve circled
7.96, the number in the
“Medium” row. Since I’ve
used numbers in the “Medium”
row in both columns 2 and 3,
I can take the figure in
column 6 for material costs
directly from the table,
without any calculations.
In
column 7, Overhead per
100 SF, I’ve calculated
the overhead dollar value by
adding the labor cost, labor
burden and material cost
then multiplying that sum by
the “Medium” overhead at 25
percent: $3.11 + $.92 +
$7.96 = $11.99 x .25 =
$3.00.
In
column 8, Profit per 100
SF, I’ve calculated the
profit dollar value by
adding the labor cost, labor
burden, material cost and
overhead then multiplying
that sum by the “Medium”
profit at 12 percent from
Figure 1. The result is
$3.11 + $.92 + $7.96 + $3.00
= $14.99 x .12 = $1.80.
Column
9, Total cost per 100 SF,
is the bid price — it’s the
sum of columns 4 through 8
for each row. Because I’ve
circled costs that fall in
more than one row, I can’t
use any figure in column 9.
Instead, I simply add the
circled or calculated
figures in columns 4 through
8: $3.11 + $.92 + $7.96 +
$3.00 + $1.80 = $16.79.
That’s my bid price per 100
square feet on this job.
It’s the combination of
costs that fit my company,
my painters and the job.
Using Your Good Judgment
Of course, judgment is
required when using these
tables, as it is when making
any estimate. For example,
if your journeymen painters
earn the top rate of $25.75
but work at the “Medium”
production rate or slower,
your labor cost per unit
will be higher than the
highest cost listed in
column 4. An adjustment will
be required.
Because figures in columns 7
and 8 are percentages of
figures in columns 4, 5 and
6, you have to be careful
when you blend costs from
different rows. Let’s look
at an extreme (and unlikely)
example.
Suppose you use costs from
the “Slow” application row
for columns 4 (3.38), 5
(.99) and 6 (8.37) of Figure
2. The total of those three
costs is $12.74. Then you
decide to use overhead from
the “Fast” row because your
overhead is about 31 percent
of cost, not 19 percent of
cost as in the “Slow” row
(Figure 1). “Fast” overhead
is listed as 3.99 in Figure
2. The correct overhead
figure is $3.95, 31 percent
of the sum of “Slow” costs
in columns 4, 5 and 6. Be
aware of this small
discrepancy and calculate
figures for all the
categories yourself if
extreme accuracy is
essential.
Converting Unit Prices
The last column in Figure 2
shows the total cost per 100
square feet of wall. Some
estimating tables in this
book show a total cost per
100 linear feet (such as for
baseboard) or total costs
per unit (such as for
doors). To convert a cost
per 100 square feet to a
cost per square foot, move
the decimal point two places
to the left. Thus the cost
per 100 square feet for the
“Fast” rate in Figure 2 is
$18.06 or about 18 cents per
square foot.
General Qualifications
It’s important that you
understand the conditions
the tables are based upon. I
call these conditions the
job qualifications. A
qualifications statement
follows each estimating
table to help you understand
what’s included and what’s
excluded. Please read those
qualifications before using
costs from this manual in
your estimates. The
following points apply to
all tables in this book:
Included Costs
-
Minor preparation, both
time and material.
Normal preparation for
new residential
construction is included
in the “Fast” row and
for new commercial jobs
in the “Medium” row.
Minimal preparation is
included for repaint
jobs in the “Slow” row.
-
Minimum setup and
cleanup
-
Equipment such as
ladders, spray rigs and
brushes are included in
overhead for the “Fast”
rate (residential
tracts) or “Medium”
(commercial) work. Add
equipment costs at their
rental rate for “Slow”
(repaint) jobs.
Excluded Costs
-
Equipment costs such as
ladders, spray rigs,
etc. for “Slow”
(repaint) jobs. Add
these at their rental
rate whether or not you
own the equipment.
-
Extensive surface
preparation. Add the
cost of time and
materials needed for
more than “normal”
preparation work. Also
add time to remove and
replace hardware and
accessories, protect
adjacent surfaces, and
do any extensive setup,
cleanup, or touchup.
(See the discussion of
SURRPTUCU on the next
page.)
-
Mobilization or
demobilization
-
Supervision
-
Material handling,
delivery, or storage
-
Sample preparation
-
Mixing coatings
-
Excessive material waste
or spillage
-
Equipment rental or
placement costs
-
Scaffolding rental and
erection costs
-
Subcontract costs
-
Contingency allowance
-
Owner allowances
-
Commissions, bonuses,
overtime, premium pay
for shift adjustments
(evening work), travel
time or per diem.
-
Bonds, fees, or permits
-
Additional insurance to
meet owner requirements
-
Work at heights above 8
feet or beyond the reach
of a wand or extension
pole.
(See the table for High
Time Difficulty Factors
on page 139.)
Surface Preparation
The Preparation estimating
tables that follow Part I:
General Painting Costs,
apply to both interior and
exterior surfaces.
Surface preparation is one
of the hardest parts of the
job to estimate accurately.
Any experienced painter can
make a reasonably good
estimate of the quantity of
paint and time needed for
application. But the amount
of prep work needed will
vary widely — especially for
repaint jobs. Some will need
very little work. Others
will take more time for prep
than for painting.
Preparation work for new
construction jobs is
relatively standard and
consistent.You’ll have to
mask cabinets before
spraying sealer on wet area
walls, caulk at the
baseboards, putty the nail
holes in wood trim, and
occasionally use a wire
brush to smooth and clean a
surface. The time required
for this work is fairly
predictable.
Labor
cost for normal preparation
of unpainted surfaces in new
residential construction is
included in the “Fast” labor
costs and for new commercial
construction in the “Medium”
labor cost. The cost of
materials for normal surface
preparation on unpainted
surfaces is included in the
sundries allowance that’s
part of the “Fast” or
“Medium” material cost.
But if
more than normal surface
prep work is needed,
estimate the extra manhours
and materials required and
add these costs to your
estimate.
Add for Repaint Preparation
The “Slow” unit costs
include no surface
preparation other than a
quick wipedown. Preparation
on a repaint job may take
longer than the painting
itself. That’s why you have
to estimate surface prep as
a separate item and add that
cost to your estimate.
A
misjudgment in estimating
preparation work can be very
expensive. That’s why I
recommend that you bid
surface preparation by the
hour, using your shop rate
for “time and material”
jobs, or some other
specified hourly rate. That
protects you against cost
overruns if the preparation
takes longer than
anticipated. But there’s a
danger here. Owners may be
angry about the cost because
they don’t understand what’s
involved in preparation and
why it takes so long.You can
avoid this with a “not to
exceed” bid that contains a
maximum price for the prep
work. Your bid should define
the scope of preparation
work in detail and list
exactly what’s included and
excluded. Be sure to
consider all the labor,
material, and equipment
costs involved.
If you
have to bid repaint work, be
sure to include all the
miscellaneous costs. The
acronym I use to identify
these miscellaneous costs is
SURRPTUCU: Setup (SU),
Remove and Replace (RR),
Protection (P), Touchup (TU)
and Cleanup (CU). Add these
costs to your repaint
estimate if they require
anything beyond minimum
attention.
-
Setup includes
unloading the vehicle,
spreading the tarp and
setting up the tools —
everything that has to
be done before prep or
painting can begin.
-
Remove and replace
everything that will
interfere with painting,
including door and
cabinet hardware, the
contents of cabinets,
light fixtures, bathroom
accessories, switch
covers and outlet
plates, among others.
-
Protection for
furniture and adjacent
surfaces such as floors,
cabinets, plumbing or
electrical fixtures,
windows, and doors.
Protection methods
include masking,
applying visqueen,
laying drop cloths and
applying a protective
coating on windows.
-
Touchup time
varies with the speed
and quality of the
painting job and how
fussy the owner is. The
more careful your
painters are, the less
touchup time needed. You
can estimate touchup
time accurately only if
you know how well your
crews perform. The
Touchup table in this
book is based on a
percentage of total job
cost.
-
Cleanup time is
usually about the same
as setup time, about 20
to 30 minutes each day
for repaint jobs.
Cleanup time begins when
work stops for the day
and ends when the crew
is back in the truck and
ready to go home. It
includes cleaning tools,
dismantling the paint
shop and loading the
vehicle.
Subcontractors
Painting contractors don’t
hire many subcontractors.
But once in a while you’ll
need a specialist for
sandblasting, waterblasting,
wallcovering, scaffolding or
pavement marking.
Subcontract costs are not
included in the estimating
tables. Add the cost of any
subcontract work that will
be required.
Figure
3 shows some typical rates
quoted by sandblasting
subcontractors. Of course,
prices in your area will
probably be different. You
could also figure
sandblasting unit costs from
the sandblasting estimating
tables included in Part II,
Preparation Costs, in this
book. Figure 3 -
Sandblasting Pricing Table
is included in the book but
not shown here.
Figure
4 shows typical subcontract
bids for pavement marking.
Again, prices in your area
may be different.
Figure 4
Pavement marking pricing
table
|
Pricing
rules of
thumb: |
|
|
|
Number of
parking
spaces:
Figure on
one space
per 300 SF
of pavement |
|
|
|
Single line
striping
with light
graphics
application |
|
$9.08 per
space |
|
Single line
striping
with heavy
graphics
application |
|
15.80 per
space |
|
Single
striping,
light
graphics and
3' wheel
stop |
|
22.50 per
space |
|
Single
striping,
heavy
graphics and
3' wheel
stop |
|
29.10 per
space |
|
|
Equipment
pricing: |
|
|
|
Simple
“inverted
spray can”
approximate
cost |
|
$204.00 |
|
Professional
striping
machine cost
range |
|
4,200 to
4,620 |
|
Professional
road/highway
striper |
|
230,000 |
|
|
Subcontractor
pricing: |
|
|
|
Move on: |
|
$137.00 to
168.00 |
|
|
Striping
prices: |
|
|
|
Single line
striping |
|
$.42 to .53
per lineal
foot |
|
Bike lane
striping |
|
.53 to .63
per lineal
foot |
|
Fire lane,
red curb |
|
.42 to .53
per lineal
foot |
|
|
Symbol
pricing: |
|
|
|
Templates -
8'0"
template |
|
$158.00 to
189.00 each |
|
Arrows |
|
35.70 to
42.00 each |
|
Handicap
symbol, one
color |
|
14.70 to
20.00 each |
|
Handicap
symbol, two
color |
|
26.30 to
31.50 each |
|
No parking
fire lane
stencil |
|
2.84 to 3.47
each |
|
|
Wheel
stops: |
|
|
|
3'0" stops |
|
$20.00 to
25.20 each
if pinned on
asphalt |
| |
|
26.30 to
31.50 each
if glued and
pinned |
|
6'0" stops |
|
31.50 to
37.80 each
if pinned on
asphalt |
| |
|
37.80 to
43.10 each
if glued and
pinned |
| |
|
(add for
stops pinned
to concrete) |
|
|
Signs and
posts: |
|
|
|
Sign only
12" x 18" |
|
$44.10 to
62.00 |
|
Post mounted
12" x 18" |
|
116.00 to
160.00 |
|
|
Pavement
markers: |
|
|
|
One way
pavement
markers |
|
$9.45 each |
|
Two way
pavement
markers |
|
12.60 each |
|
If you do much repainting, you’ll probably
want to buy a waterblasting
rig. Even if you own the
blaster, include a charge in
each estimate for the
equipment as though you
rented it from a rental yard
just for that job. Figure
the unit costs for
waterblasting from Part II
of this book, Preparation
Costs.
Consider using a
waterblasting subcontractor
if you don’t need the
service often. Figure 5
shows some typical rates for
waterblasting. Make up a
table like this based on
quotes from subcontractors
in your area. For a more
detailed table, see
Sandblasting in the
Preparation section, page
303.
When
you hire a subcontractor,
make sure the quoted price
includes everything that
contractor has to do — all
labor, material (with tax,
if applicable), equipment,
overhead and profit. Add
your overhead and profit
percentage to the
subcontractor’s bid price
when you enter that item on
the estimate.
Contingencies
Occasionally you’ll add a
contingency allowance on
bids for repaint projects
where there are unknowns
that can’t be forecast
before work actually begins.
Contingency allowances are
rarely needed when
estimating new construction.
When necessary, the
contingency amount is
usually from 3 to 5 percent.
It can go higher, however,
if there are unusual
conditions or unknowns that
make it hard to produce an
accurate estimate. Include a
contingency allowance in
your estimates only if you
have reason to expect:
-
An uncertain scope of
work (unknown job
conditions)
-
An inexperienced owner
or general contractor
-
Incomplete drawings
-
Delays in beginning the
project
-
Owner involvement in
supervision
-
Below-standard working
conditions
Don’t
use contingency allowances
as a substitute for complete
estimates. Include
contingency only to cover
what can’t be estimated, not
what you don’t have time to
estimate accurately.
Figure 5
Waterblasting pricing
table
|
Minimum
charges:
$525.00,
scaffolding
not included |
|
Additional
insurance:
May be
required to
cover
adjacent
personal and
real
property |
|
Pricing
rules of
thumb: |
|
|
|
Up to 5,000
PSI blast |
|
4 hour
minimum
$116.00/hour |
|
5,000 to
10,000 PSI
blast |
|
8 hour
minimum
$168.00/hour |
|
10,000 PSI
blast |
|
8 hour
minimum
$208.00/hour |
|
Wet
sandblasting |
|
4 hour
minimum
$133.00/hour |
|
-
We
will stop the chapter
sample here on page 13.
The remaining 28 pages
of this chapter
thoroughly cover the
topics of:
-
labor productivity,
-
supervision,
-
material coverage,
-
material pricing,
-
material costs,
-
labor costs,
-
overhead,
-
equipment rental rates,
-
profit,
-
profit margin,
-
risk factors,
-
bidding variables
-
and total cost -
including many charts
and figures.
|