This Book Is an Encyclopedia
of Concrete and Masonry Estimating
Data
Estimating concrete and masonry
costs requires specialized skills.
You can't price concrete and masonry
work the same way you would price
carpentry, plumbing or electrical
work. The proportion of labor
expense is greater. There's more
risk because there are more
variables and unknowns.
The sections
that follow have detailed labor,
material and equipment costs for
nearly all common concrete and
masonry work. Emphasis will be on
avoiding risk -- pricing pitfalls
that can turn any concrete and
masonry job into a financial
nightmare.
Concrete and
Masonry Are Unique
Both concrete and masonry are
heavy. The heavier the material, the
more labor and specialized equipment
needed to complete each unit of
work. Experienced estimators will
agree that labor is the most
difficult cost component to estimate
accurately. That places concrete and
masonry among the most demanding of
the construction trades to estimate
precisely.
For example,
the cost of laying block increases
as wall height increases, even when
lifting equipment is on hand and is
used to good advantage. Your crews
are going to lay more block per hour
when the wall is 4 feet high than
when the same wall tops out at 18 or
20 feet above ground level. It's
poor practice to assume the same
labor productivity per block
regardless of wall height. Masonry
and concrete estimates that don't
consider changes in labor
productivity as wall height
increases are likely to miss the
mark by a wide margin.
How This
Manual Will Help
Most concrete and masonry
estimators wear several hats. Many
serve as company manager, owner,
chief estimator, project manager and
field superintendent. With roles
like that, there may be no time to
do a detailed labor and material
take-off for every job that comes
along. Even a full-time estimator
may not have ample time to do a
detailed take-off on every job.
If you're an
experienced concrete and masonry
estimator with too little time to
scope out the last dime of cost in
every job, take heart. This book is
for you. I've done most of tedious
work already. Use my figures to save
time, save effort, and eliminate
most of the routine mistakes even
seasoned estimators make at least
occasionally.
If you've had
years of experience with concrete
and masonry in the field, but little
or no estimating experience, this
book is likely to be the best guide
you'll find anywhere. Cost data in
this manual was compiled by a
mathematician with almost three
decades of estimating experience.
Most of the cost tables in this
manual are for complete assemblies
-- such as block, reinforcing, and
grout -- all wrapped up into one
convenient package ready for use.
Using these assembly costs will give
you extra time to estimate more
jobs, run projects more effectively,
and be a better manager for your
growing business.
No Price Fits
All Jobs
There’s no single way to arrive at
the correct price for concrete and
masonry work. Neither is there a
single correct price for most
concrete and masonry projects. But
there are both good and bad ways to
estimate prices and there are good
and bad prices for any proposed job.
Your task as a concrete and masonry
estimator is to produce consistently
good estimates on most jobs. If
you're not, the information on the
following pages will make or save
you many times the cost of this
manual.
Throughout
this book you'll find pictures and
examples that make your work easier.
It's nearly impossible to estimate
costs for work you can't visualize
and don't understand.
Of course, the
best price book for your company
would be based on your actual cost
experience -- work done on your jobs
with materials from dealers and
installed by your crews or
subcontractors. Since every
contractor uses different crews,
subcontractors and suppliers, every
price book should be different. And,
of course, prices in the company
price book should be revised
regularly to reflect current labor
and material costs.
Save
Estimating Effort
Having admitted that there's no
substitute for developing your own
price book, I'll suggest that you
not bother. Most concrete and
masonry contractors don't have the
time or patience to maintain current
installed prices for every type of
block, brick and concrete job. Even
if you did, spending hundreds of
hours a year keeping a price book
current would be a waste of time.
Instead, I
suggest that you let this manual
serve as your company price book.
Using prices in this book (and on
the National Estimator disk in the
back of the book) will eliminate
most of the common estimating
mistakes. If your labor costs are
higher or if your crews aren't as
skilled as most tradesmen, you may
have to increase the prices listed
here to make a reasonable profit.
And, of course, sometimes you're
going to have a job with costs that
exceed what any reasonable estimate
could have predicted. This manual
isn't a substitution for the
exercise of good judgment. That's
always your job.
This Book
Works Two Ways
The disk in
the back of this book has all the
same information that appears in the
printed book, but with one
advantage. The National Estimator
program makes it easy to copy and
paste these costs into an estimate
(or bid) and then add whatever
markup you select. To get started
with the National Estimator disk,
insert it into any computer that
uses Microsoft Windows. Then follow
the instructions on the screen. If
you have trouble using National
Estimator, call 760-438-7828 8 AM
to 5 PM (Pacific), Monday through
Friday. We’ll be glad to help.
Before
installation is complete, you’ll be
invited to watch ShowMe, an
interactive video guide to the
National Estimator program.
ShowMe is designed to speed your
mastery of National Estimator. You
can also start ShowMe at any
time while using National Estimator.
Click the question mark button at
the right end of the toolbar. Then
click “ShowMe Tutorial.” The
installation disk has to be in your
computer when ShowMe is
running.
Once an
estimate is finished in the National
Estimator program and saved to disk,
press Ctrl. on your keyboard and tap
the letter J to convert the estimate
into a proposal in Job Cost Wizard.
You can’t make changes in the Job
Cost Wizard screen. But it’s easy to
toggle back to the National
Estimator program (press Alt. and
tap the Tab key), make a change, and
then press CtrlJ once again.
Job Cost
Wizard offers dozens of choices
on what you show and don’t show in
written proposals. Your bids can be
long (full description for
everything in the estimate) or short
(only a summary of each category).
You can show or hide labor and
material cost details. You can show
or hide markup and profit.
Once work
begins, you’ll want to monitor job
expenses to be sure actual costs
remain consistent with estimated
costs. If you use QuickBooks Pro to
pay bills and figure payroll, let
QuickBooks do the comparisons
for you. Job Cost Wizard exports the
proposal to QuickBooks, where you
can prepare progress invoices and
track expenses against estimates.
The National
Estimator program lets you change
anything in the costbook or even add
your own estimated costs.
Let the National Concrete &
Masonry Estimator costbook
become your collection point for all
estimating and pricing information.
Anything you add to the costbook
shows up in red and can be migrated
to later editions of this manual
when available. The National
Concrete & Masonry Estimator
costbook starts out as your most
useful estimating reference. What
you add to that costbook will make
it even more valuable.
Material
Costs in This Book
Material costs
for each item are listed in the
column headed “Material.” These are
neither retail nor wholesale prices.
They are estimates of what most
contractors who buy in moderate
volume will pay suppliers as of
mid2007. Discounts may be available
for purchases in larger volumes.
Add
Delivery Expense to the material
cost for other than local delivery
of reasonably large quantities. Cost
of delivery varies with the distance
from source of supply, method of
transportation, and quantity to be
delivered. But most material dealers
absorb the delivery cost on local
delivery (5 to 15 miles) of larger
quantities to good customers. Add
the expense of job site delivery
when it is a significant part of the
material cost.
Add Sales
Tax when sales tax will be
charged to the contractor buying the
materials. In some states,
contractors have to collect sales
tax based on the contract price. No
matter what your state (or county)
requires, National Estimator can
handle the task. Click Edit on the
National Estimator menu bar. Then
click Sales Tax.
Waste and
Coverage loss is included in the
installed material cost. The cost of
many materials per unit after
installation is greater than the
purchase price for the same unit
because of waste, shrinkage or
coverage loss during installation.
For example, 1.125 concrete block
are needed to create a square foot
of wall. But it’s good estimating
practice to order about 5% more
block than required for the job.
Some block will be broken before
they can be set in place (waste). A
few block will be pulled off the
pile for use as wheel stops or
holddowns (shrinkage). And some
block will have to be cut to fit
around corners, doors and windows
(coverage loss). There is no
coverage loss with concrete. But
it’s common to need a little extra
concrete to accommodate
overexcavation.
Costs in the
“Material” column of this book
assume normal waste and coverage
loss. Small and irregular jobs may
require a greater waste allowance.
Materials priced without
installation (with no labor cost) do
not include an allowance for waste
and coverage except as noted.
Labor Costs
Labor costs
for installing the material or doing
the work described are listed in the
column headed “Labor.” The labor
cost per unit is the labor cost per
hour multiplied by the manhours per
unit shown after the @ sign in the
“Craft @ Hours” column. Labor cost
includes the basic wage, the
employer’s contribution to welfare,
pension, vacation and apprentice
funds and all tax and insurance
charges based on wages.
Supervision
Expense to the general
contractor is not included in the
labor cost. The cost of supervision
and nonproductive labor varies
widely from job to job. Calculate
the cost of supervision and
nonproductive labor and add this to
the estimate.
Payroll
Taxes and Insurance are included
in the labor cost. See the following
section for more on the
“contractor’s burden.”
Manhours
per Unit and the Craft
performing the work are listed in
the “Craft @ Hrs” column. To find
the units of work done per man in an
8hour day, divide 8 by the manhours
per unit. To find the units done by
a crew in an 8hour day, multiply
the units per man per 8hour day by
the number of crew members.
Manhours
Include all productive labor
normally associated with installing
the materials described. This will
usually include tasks such as:
- Unloading
and storing materials, tools and
equipment on site.
- Moving
tools and equipment from a
storage area or truck on site at
the beginning of the day.
- Returning
tools and equipment to a storage
area or truck on site at the end
of the day.
- Normal
time lost for work breaks.
- Planning
and discussing the work to be
performed.
- Normal
handling, measuring, cutting and
fitting.
- Keeping a
record of the time spent and
work done.
- Regular
cleanup of construction debris.
-
Infrequent correction or repairs
required because of faulty
installation.
Adjust the
Labor Cost to the job you are
figuring when your actual hourly
labor cost is known or can be
estimated. The labor costs listed in
the following section will apply
within a few percent on many jobs.
But labor costs may be much higher
or much lower on the job you are
estimating.
If the hourly
wage rates listed in the following
section are not accurate, divide
your known or estimated cost per
hour by the listed cost per hour.
The result is your adjustment for
any figure in the “Labor” column for
that craft.
Adjust for
Unusual Labor Productivity.
Costs in the labor column are for
normal conditions: experienced
craftsmen working on reasonably
wellplanned and managed concrete
and masonry projects with fair to
good productivity. Labor estimates
assume that materials are standard
grade, appropriate tools are on
hand, work done by other crafts is
adequate, layout and installation
are relatively uncomplicated, and
working conditions don’t slow
progress.
Working
conditions at the job site have a
major effect on labor cost.
Estimating experience and careful
analysis can help you predict the
effect of most changes in working
conditions. Obviously, no single
adjustment will apply on all jobs.
But the adjustments that follow
should help you produce more
accurate labor estimates. More than
one condition may apply on a job. .
- Add 10%
to 15% when working temperatures
are below 40 degrees or above 95
degrees.
- Deduct
10% when the work is in an open
area with excellent access and
good light.
- Add 5% to
50% for tradesmen with below
average skills. Deduct 5% to 25%
for highly motivated, highly
skilled tradesmen.
- Deduct
10% to 20% when an identical
task is repeated many times for
several days at the same site.
- Add 20%
to 50% on small jobs where
fitting and matching of
materials is required, adjacent
surfaces have to be protected
and the job site is occupied
during construction.
- Add 25%
to 50% for work done following a
major flood, fire, earthquake,
hurricane or tornado while
skilled tradesmen are not
readily available. Material
costs may also be higher after a
major disaster.
- Add 10%
to 35% for demanding specs,
rigid inspections, unreliable
suppliers, a difficult owner or
an inexperienced architect.
This manual
has been compiled by and for
concrete and masonry estimators, not
engineers. Nothing in this manual is
intended to suggest approved or
recommended engineering practice.
Only an engineer licensed to
practice in your community can
identify materials and procedures
that meet code requirements and
accepted standards for reinforcing
steel, structural concrete and
structural masonry.
Use an Area
Modification Factor from pages 8
through 11 if your material, hourly
labor or equipment costs are unknown
and can’t be estimated. Here’s how:
Use the labor and material costs in
this manual without modification.
Then add or deduct the percentages
shown for labor, material and
equipment.
Equipment
Costs for small tools and
expendable supplies (such as towels
and tape) are usually considered
overhead expense and are covered by
your markup. Equipment costs for
larger equipment (such as a forklift
or backhoe)should be based on the
rental rate for the period needed.
Equipment costs are included in
sections where heavy equipment may
be needed.
Labor and
Material Costs Change. These
costs were compiled in the fall of
2005 and projected to mid2006 by
adding a small percentage. This
projection will be accurate for some
materials and inaccurate for others.
No one can predict material price
changes accurately.
How
Accurate Are These Figures? As
accurate as possible considering
that the estimator who wrote this
book doesn’t know your
subcontractors or material
suppliers, hasn’t seen the plans or
specifications, doesn’t know what
building code applies or where the
job is, had to project material
costs at least six months into the
future, and had no record of how
much work you crews can handle.
You wouldn’t
bid a job under those conditions.
And I don’t claim that all
construction is done at these
prices.
Estimating
Is an Art, not a science. On
many jobs the range between high and
low bid will be 20% or more. There’s
room for legitimate disagreement on
what the correct costs are, even
when complete plans and
specifications are available, the
date and site are established, and
labor and material costs are
identical for all bidders.
No cost fits
all jobs. Good estimates are custom
made for a particular project and a
single contractor through judgment,
analysis and experience.
This book is
not a substitute for judgment,
analysis and sound estimating
practice. It’s an aid in developing
an informed opinion of cost. If
you’re using this book as your sole
cost authority for contract bids,
you’re reading more into these
pages than the author intends.
Use These
Figures to compile preliminary
estimates, to check your costs and
subcontract bids and when no actual
costs are available. This book will
reduce the chance of error or
omission on bid estimates, speed
“ball park” estimates, and be a good
guide when there’s no time to get a
quote.
Where Do
These Figures Come From? From
the same sources all professional
estimators use: material suppliers,
material price services, analysis of
plans, specifications, estimates and
completed project costs, and both
published and unpublished cost
studies compiled by both private
and government agencies.
Labor Costs
and Crews
Throughout
this manual you’ll see a column
headed Craft @ Hrs. Letters and
numbers in this column show our
estimates of:
- Who will
do the work (the craft code) .
- An @
symbol, which means “at” .
- How long
the work will take (manhours).
For example,
at the top of page 23 you’ll find
estimates for installing common
brick. The Craft @ Hrs column under
6'0" high wall and opposite “Cost
per square foot” shows:
B9 @ .232
That means we
estimate the installation time for
crew B9 at .232 manhours per square
foot of wall. That’s the same as
23.2 manhours per 100 square feet.
The Craft
Codes table below defines each of
the craft codes used in this book.
Notice that crew B9 is composed of
one bricklayer and one bricklayer’s
helper. To install 100 square feet
of common brick in a 6'0" high wall
would require 23.2 manhours (11.6
hours for a crew of two).
Notice also in
the table below that the cost per
manhour for crew B9 is listed as
$27.96. That’s the average for a
bricklayer (listed at $31.76 per
hour on page 7) and a helper (listed
at $24.15 per hour). Add $31.76 and
$24.15 to get $55.91. Divide by 2 to
get $27.96, the average cost per
manhour for crew B9.
Costs in the
labor column of this book are the
product of the installation time (in
manhours) multiplied by the cost per
manhour. For example, on page 23 the
labor cost listed for a 6'0" high
wall is $6.49 per square foot.
That’s the installed time (.232
manhours) multiplied by $27.96, the
average cost per manhour for crew
B9.
The next table
shows hourly labor cost components
base wage, typical fringe benefits,
payroll taxes, insurance, and the
total hourly cost.
|
Craft Code |
Cost Per MH |
Crew Composition
|
|
B1 |
$30.35 |
1 laborer, 1 carpenter
|
|
B2 |
$31.32 |
1 laborer, 2 carpenters
|
|
B3 |
$29.38 |
2 laborers, 1 carpenter
|
|
B6 |
$29.49 |
1 laborer, 1 cement mason
|
|
B8 |
$32.35 |
1 laborer 1 operating
engineer |
|
B9 |
$29.71 |
1 bricklayer 1 bricklayer’s
helper |
|
BA |
$30.71 |
2 building laborers 1
operating engineer
|
|
BC |
$33.27 |
1 carpenter |
|
BL |
$27.43 |
1 building laborer
|
|
BV |
$30.93 |
3 carpenters, 2 laborers
|
|
F5 |
$42.90 |
2 building laborers 3
carpenters |
|
RI |
$32.01 |
1 reinforcing iron worker
|
|
T7 |
$27.59 |
1 carpenter, 3 laborers 1
operating engineer, 1 truck
driver |
Craft Codes
Used in This Manual
| |
1 |
2 |
3 |
4 |
5 |
6 |
|
Craft |
Base wage per hour |
Taxable fringe benefits
(@ 5.15% of base wage) |
Insurance and
employer
taxes (5%) |
Insurance and
employer
taxes ($) |
Nontaxable
fringe benefits (@ 0.05 base
wage) |
Total hourly
cost used in this book
|
|
Bricklayer |
24.70 |
1.27 |
25.54% |
6.63 |
1.12 |
33.72 |
|
Bricklayer’s Helper
|
18.81 |
.97 |
25.54% |
5.05 |
0.86 |
25.69 |
|
Building Laborer |
19.01 |
0.98 |
32.93% |
6.58 |
0.86 |
27.43 |
|
Carpenter |
23.23 |
1.20 |
31.83% |
7.78 |
1.06 |
33.27 |
|
Cement Mason |
23.49 |
1.21 |
23.35% |
5.77 |
1.07 |
31.54 |
|
Operating Engineer |
27.32 |
1.41 |
25.42% |
7.30 |
1.24 |
37.27 |
|
Reinforcing Ironworker |
22.86 |
1.18 |
28.81% |
6.93 |
1.04 |
32.01 |
|
Truck Driver |
19.98 |
1.03 |
26.42% |
5.55 |
0.91 |
27.47 |
Hourly Labor
Costs
Components
of Hourly Labor Costs
The labor
costs shown in Column 6 were used to
compute the manhour costs for crews
on page 6 and the figures in the
“Labor” column.
It’s important
that you understand what’s included
in the figures in each of the six
columns above. Here’s an
explanation:
Column 1,
the base wage per hour, is the
craftsman’s hourly wage. These
figures are representative of what
many contractors will be paying
craftsmen working on concrete and
masonry jobs in 2006.
Column 2,
taxable fringe benefits,
includes vacation pay, sick leave
and other taxable benefits. These
fringe benefits average 5.15% of the
base wage for many construction
contractors. This benefit is in
addition to the base wage.
Column 3,
insurance and employer taxes in
percent, shows the insurance and tax
rate for construction trades. The
cost of insurance in this column
includes workers’ compensation and
contractor’s casualty and liability
coverage. Insurance rates vary
widely from state to state and
depend on a contractor’s loss
experience. Note that taxes and
insurance increase the hourly labor
cost by 30 to 35% for most trades.
There is no legal way to avoid these
costs.
Column 4,
insurance and employer taxes in
dollars, shows the hourly cost of
taxes and insurance for each
construction trade. Insurance and
taxes are paid on the costs in both
columns 1 and 2.
Column 5,
nontaxable fringe benefits,
includes employer paid nontaxable
benefits such as medical coverage
and taxdeferred pension and profit
sharing plans. These fringe benefits
average 4.55% of the base wage for
many construction contractors. The
employer pays no taxes or insurance
on these benefits.
Column 6,
the total hourly cost in dollars, is
the sum of columns 1, 2, 4, and 5.
These hourly
labor costs will apply within a few
percent on many jobs. But wage rates
may be much higher or lower in the
area where you do business. We
recommend using your actual labor
cost rather than national averages.
That’s easy with the National
Estimator program. When copying and
pasting any cost to your estimate,
adjust the assumed hourly labor cost
to your actual cost. You need do
this only once for each trade. And
you can make this adjustment at any
time. Any change you make is applied
to that trade throughout the
estimate |